Offices

West Quay

West Quay
Previous
  • West Quay 1
  • West Quay 2
  • West Quay 3
  • West Quay 4
  • West Quay 5
  • West Quay 6
  • West Quay 7
Next

Key Information

Location: Southampton

Cost: £40 million

Size: 220,300 sq ft

Duration: 112 weeks

Additional Information: Client: Development Securities

Built for Development Securities, this office accommodation is Carnival Cruise’s Headquarters.

The Category A building boasts five floors around a central atrium, an ETFE roof, a rooftop viewing gallery and provides car parking for 86 cars.  Works were executed in a live city centre environment – the adjacent West Quay Road is a major traffic artery and the site is also next to a major retail mall and the entrance to a very active multi-storey car park.

We were also appointed to undertake the fast-track quality fit-out works.

This project was a finalist in the 2009 Construction News Quality Awards.

 

 

"They exceeded our expectations in every aspect, delivering a quality building six weeks ahead of an aggressive programme and within budget.

"From the first meeting to the last, Miller maintained an integrity in everything they did."

Duncan Trench, Head of Delivery, Development Securities Plc



"The award of the fitting out contract to Miller Construction was not based upon price (as there was no significant variation between the bids), but upon the quality, experience and positive attitude of the management team, the exemplary control and quality demonstrated during the construction of the shell and core and Category A works.

"The project was awarded an 'Excellent’ rating by Carnival UK as part of a very detailed Post Project Review. The achievement of this rating was in no small part due to Miller Construction's performance."

A Clarke, Director, Corporate Accommodation